Human Resource & AdministrationFactors impacting Contingency: A Study onConstruction of Substations in UAE

Sreenivasan Lakshmanan, Dr. Joji Rao Thadi, Dr. Sumeet Gupta

Abstract


Purpose

To identify the significant risk factors related to the Human Resource & Administration,which are impacting the project performance due to contingency estimation for the construction of substations in United Arab Emirates.

Design / Methodology / Approach

A structured questionnaire for Human Resource & Administration sectionwith 14questionswas prepared for response in 5 point scale of Importance.  The questionnaire was distributed by means of electronic mail and paper prints.  The responses were received by e-mail, by hand& by telephonic conversations.  These responses were further analyzed using Factor Analysis in SPSS.

Findings

A condensed list of 5 significant risk factors was identified out of the original 14 risk factors in the Human Resource & Administration section, based on their importance, as received from various respondents,after carrying out factor analysis of the responses.

Research Limitation / Implication

The present study provides a list of significant risk factors faced in the construction of substations in United Arab Emirates, which is being taken up for further research to check the impact of the contingency perception of these risk factors on the project performance in terms of Time and Cost.  The findings and result are related to the Human Resource & Administrationsection of the Questionnaire.

Originality / value

This research provides an output that is very useful for organizations involved in construction of substations projects in United Arab Emirates for taking up these risk factors for a detailed analysis and adopting a suitable mitigation plan for improving the project performance.

 

Keywords: Project Management, Risk factors, Contingency, Substations, UAE


References


AECOM report, ‘Middle East’s Construction Handbook (2013)’. www.aecom.com.

Abdullah Albogamy, Darren Scott, NashwanDawood&GhanimBekr, (2013) ‘Addressing Crucial Risk Factors In The Middle East Construction Industries: A Comparative Study Of Saudi Arabia And Jordan’, Sustainable Building Conference 2013, Coventry University,page 118 to 128.

Adnan Enshassi, Sherif Mohamed, Saleh Abushaban, (2009) ‘Factors Affecting The Performance Of Construction Projects In The Gaza Strip’, Journal Of Civil Engineering And Management, 2009, 15(3): 269–280, DOI: 10.3846/1392-3730.2009.15.269-280.

Alfred E. Thal Jr.; Jason J. Cook; and Edward D. White III, (2010) ‘Estimation of Cost Contingency for Air Force Construction Projects’, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE, November 2010, page 1181 to 1188, DOI: 10.1061/ ASCE CO.1943-7862.0000227.

Anna Klemetti, (2006) ‘Risk Management in Construction Project Networks’, Helsinki University of Technology, Laboratory of Industrial Management - Report 2006/2.

ArshiShakeelFaridi&SamehMonir El-Sayegh, (2006) ‘Significant factors causing delay in the UAE construction industry’, Construction Management and Economics, (November 2006) 24, 1167–1176, DOI: 10.1080/01446190600827033.

B.P. Sunjka and U. Jacob, (2013) ‘Significant Causes And Effects Of Project Delays In The Niger Delta Region, Nigeria’, SAIIE25 Proceedings, 9th – 11th of July 2013, Stellenbosch, South Africa © 2013 SAIIE, page 641 -1 to 641-14.

Baydoun, M. (2011), ‘Risk management of large-scale development projects in developing countries: Cases from MDI’s projects’, International Journal of Technology Management and Sustainable Development, 9: 3, pp. 237–249, doi: 10.1386/tmsd.9.3.237_1

Bentler, P. M. & Chou, C. P. (1987) ‘Practical issues in structural modeling’, Sociological Methods & Research, 16; 78, page78-117, DOI: 10.1177/0049124187016001004.

BusinessDictionary, webpage content http://www.businessdictionary.com/definition/project.htmlAccessed on 10th April 2015, 16:01 Hrs. (UAE standard time)

Chidambaram Ramanathan, SP Narayanan &Arazi B Idrus, (2012) ‘Construction Delays Causing Risks on Time and Cost - a Critical Review’, Australasian Journal of Construction Economics and Building, 12 (1) 37-57 (2012).

Dan BENȚA (2011), ‘Software Development And Risk Management In Complex Projects’, BABEŞ-BOLYAI UNIVERSITY OF CLUJ-NAPOCA - PhD. Thesis (September 2011).

David James Bryde, and Jurgen Marc Volm, (2009), ‘Perceptions of owners in German construction projects: congruence with project risk theory’,Construction Management and Economics (November 2009) 27, 1059–1071, ISSN 0144-6193 print/ISSN 1466-433X online © 2009 Taylor & Francis, DOI: 10.1080/01446190903222403

Dr. Dan Patterson, (2006) ‘Managing Project Cost Risk’, 2006 AACE International Transactions, 2006 - IT.05, page 1-7.

Dr. Khaled Nassar, (2002), ‘Cost Contingency Analysis for Construction Projects Using Spreadsheets’, Cost Engineering, Vol. 44/No. 9 SEPTEMBER 2002, page 26-31.

Deloitte GCC Power of Construction report (2013), ‘Meeting the challenges of delivering mega projects’, Deloitte &Touche (M.E.) www.deloitte.com/middleeast

EC Harris’s report (November 2013), ‘Middle East Major Construction Programmes – Mitigating the Delivery Risk’. EC HARRIS, BUILT ASSET CONSULTANCY. www.echarris.com/middleeast

Ekaterina Osipova (2008), ‘Risk management in construction projects: a comparative study of the different procurement options in Sweden’, LICENTIATE TH ES I S 2008:15.

Francis, Adam J. and Skitmore, Martin (2005), ‘Risk management within the electrical distribution supply industry in South East Queensland ‘, Journal of Financial Management of Property and Construction, 10(1):pp. 45-53, http://eprints.qut.edu.au.

Francisco Pérez-González and Hayong Yun (2010), ‘Risk Management and Firm Value: Evidence from Weather Derivatives’, JEL classification: G30, G32, Electronic copy available at: http://ssrn.com/abstract=1357385

FLYNN, L. & PEARCY, D., (2001), ‘Four subtle sins in scale development: Some suggestions for strengthening the current paradigm’, International Journal of Market Research, 43: (4) 409-433.

Gabriel A. Barraza, (2011) ‘Probabilistic Estimation and Allocation of Project Time Contingency’, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT © ASCE, April 2011, PAGE 259 TO 265, DOI: 10.1061/(ASCE)CO.1943-7862.0000280.

Ghaleb J. Sweis, RatebSweis, Malek Abu Rumman, Ruba Abu Hussein, Samer E. Dahiyat (2013) ‘Cost Overruns in Public Construction Projects: The Case of Jordan’, Journal of American Science, 9(7s) (2013) 134–141, (ISSN: 1545-1003).www.jofamericanscience.org.

Hair JF, Tatham RL, Anderson RE and Black W (1998), ‘Multivariate data analysis’, Fifth Ed.,Prentice-Hall:London.

HAIR, J. F., BLACK, W. C., BABIN, B. J. & ANDERSON, R. E. (2010), ‘Multivariate Data Analysis: A Global Perspective’, New Jersey, Pearson Prentice Hall.

Hans Thamhain, (2013) ‘Managing Risks in Complex Projects’, Project Management Journal, Vol 44, No. 2, April 2013, DOI : 10.1002/pmj.21325, page 20 - 35.

Hughes, W. (2001), Roles in construction projects: Analysis & Terminology’, A Research Report undertaken for the Joint Contracts Tribunal Limited, JCT.

Keane, P. J. &Caletka, A. F, (2008), ‘Delay Analysis in Construction Contracts’, Oxford: Wiley-Blackwell, ISBN: 978-1-4051-5654-7.

Latham, Sir Michael (1994), ‘Constructing the team’, HMSO, London

Long Le-Hoai, Young Dai Lee, and Jun Yong Lee, (2008) ‘Delay and Cost Overruns in Vietnam Large Construction Projects : A Comparison with Other Selected Countries’, SCE Journal of Civil Engineering, (2008) 12(6):367-377.

Mamoon M. Atout, (2013) ‘Factors Caused By Consultant Engineers Affecting Project Progress’, International Conference on Management and Information Systems, September 22-24, 2013, PAGE 327 - 337.

Mohamed K. Khedr, (2006) ‘Project Risk Management Using Monte Carlo Simulation’, 2006 AACE International Transactions, RISK.02, page 1-10.

Mohammad A. Mustafa, and Jamal F. Al-Bahar, (1991) ‘Project Risk Assessment using the Analytic Hierarchy Process’, IEEE Transactions On Engineering Management, VOL. 38, NO. I , FEBRUARY 1991.

Motaleb, O and Kishk, M, (2010) ‘An Investigation Into Causes And Effects Of Construction Delays In UAE’, Egbu, C. (Ed) Procs 26th Annual ARCOM Conference, 6-8 September 2010, Leeds, UKAssociation of Researchers in Construction Management, 1149-1157.

Nie-JiaYau and Jyh-Bin Yang, (2012) ‘Factors Causing Design Schedule Delays in Turnkey Projects in Taiwan: An Empirical Study of Power Distribution Substation Projects’, Project Management Journal, Vol 43, No. 3, June 2012, DOI: 10.1002/pmj.21265, page 50 - 61.

NidaAzhar, Rizwan U. Farooqui and Syed M. Ahmed, (2008) ‘Cost Overrun Factors In Construction Industry of Pakistan’, First International Conference on Construction In Developing Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research & Practice”, August 4-5, 2008, Karachi, Pakistan, page 499 – 508.

‘Otahuhu Substation Diversity Project - Application For Increase Of Major Capex Allowance’, Transpower New Zealand Limited, (2012), September 2012.

PMBoK Guide – Fifth Edition (2013), Project Management Institute – USA.

PWC report (December 2012), ‘Delivering the Middle East’s Mega Projects 2012 Capital Projects and Infrastructure Survey’. www.pwc.com/middle-east.

QAQISH, TAMER,AYOUB (2011), ‘Cost Risk Management for a Small to Medium-sized Enterprise in the Cladding Industry’, Durham Theses, Durham University. Available at Durham E-Theses Online: http://etheses.dur.ac.uk/1380/

Rasool MEHDIZADEHN (2012), ‘Dynamic and multi-perspective risk management of construction projects using tailor-made Risk Breakdown Structures’, Thèse de DoctoratPresentée à L’UNIVERSITE BORDEAUX 1, N° d‟ordere: 4521.

Ruqaya Al-Sabah, Carol C. Menassa, Awad Hanna, (2012) ‘Evaluating Significant Risks In The Middle East North Africa (MENA) Construction Projects From Perspective Of Multinational Firms’, Proceedings of the CIB W78 2012: 29th International Conference –Beirut, Lebanon, 17-19 October 2012.

Sadi A. Assaf ,Sadiq Al-Hejji, (2006) ‘Causes of delay in large construction projects’, International Journal of Project Management, 24 (2006) 349–357, doi:10.1016/j.ijproman.2005.11.010.

Shaun Frazerhurst, Neil Watson, (2013) ‘North Auckland and Northland Grid Upgrade Project: A First for New Zealand’, PMINZ Conference Proceedings 2013, Thursday 12th September 2013, page 1-5.

SumitDatta, S.K. Mukherjee, (2001) ‘Developing a Risk Management Matrix for Effective Project Planning - Am Emprical Study’, Project Management Journal, June 2001, Vol.32, No.2, page 45-57.

Taylor Hazel, (2005) ‘Congruence between risk management theory and practice in Hong Kong vendor-driven IT projects’, International Journal of Project Management,08/2005; 23(6):437-444. DOI: 10.1016/j.ijproman.2005.02.001.

The World Development Report 2014 (WDR 2014), ‘Risk and Opportunity—Managing Risk for Development’, A World Bank Group Corporate Flagship, THE WORLD BANK, Washington DC.

V M Rao Tummala, John F Burchett, (1999) ‘Applying a Risk Management Process (RMP) to manage cost risk for an EHV transmission line project’, International Journal of Project Management, Vol. 17, No. 4, pp. 223-235, 1999, PII: S0263-7863(98)00038-6.

Wikipedia, webpage content http://en.wikipedia.org/wiki/Cronbach%27s_alpha Accessed on 8th April 2015, 16:43 Hrs. (UAE standard time)

Wikipedia, webpage content http://en.wikipedia.org/wiki/Cost_contingencyAccessed on 10th April 2015, 16:05 Hrs. (UAE standard time)

William Imbeah; and Seth Guikema, (2009) ‘Managing Construction Projects Using the Advanced Programmatic Risk Analysis and Management Model’, Journal of Construction Engineering and Management, Vol. 135, No. 8, August 1, 2009 ©ASCE, ISSN 0733-9364/2009/8-772–781. DOI: 10.1061/(ASCE)0733-9364(2009)135:8(772).

Z. Ren, M. Atout and J. Jones, (2008) ‘root causes of construction project Delays in DUBAI’, Dainty, A (Ed) Procs 24th Annual ARCOM Conference, 1-3 September 2008, Cardiff, UK, Association of Researchers in Construction Management, 749-757.